Many Paving Projects Set For Terre Haute In 2027

street-paving-jpg-5

TERRE HAUTE, Ind. – Terre Haute drivers could see fewer road projects next year as state funding cuts hit local paving plans.

State law recently capped and reduced total grant funding across Indiana.

Mayor Brandon Sakbun said the city received just over $317,000 from the state’s Community Crossings grant program. The city had requested $1 million.

Combined with casino revenue and taxes, Terre Haute plans to spend $3.9 million on paving in 2027. That is up more than 33% from 2023.

Sakbun said rising inflation, fuel and labor costs mean the money will not go as far.

The city plans to adopt a local wheel tax by next summer to qualify for additional state road funds.

City of Terre Haute — 2027 Pavement Plan

Proposed street paving and preservation projects across the city:

Pavement Plan 2027:

Community Crossings Projects

25th St – 215 Feet S of Hulman St to College

Brown Blvd – Locust St to 172 Feet S of Maple

Farrington St – 14th St to 19th St

14th St – College Ave to Poplar

Remaining Paving Funds

Mill/Pave (City Funded)

New Margaret Ave – West Side of Target to SR46

25th St – Poplar to 200 Ft South (Reconstruction)

19th St – Wabash Ave to Chestnut (Widening)

Putnam St – 16th St to 17th (Widening)

Fruitridge Ave – Trail Improvement Paving

Fruitridge Ave – RR to Poplar

Poplar St – Fruitridge to 537 Ft West of Keane Lane

8th St – Margaret Ave to Pugh

Pugh St – 8th St to 13th St

9th St – Margaret Ave to Pugh

9th 1/2 St – Margaret Ave to Dead End

10th St – Margaret Ave to Dead End

11th St – Margaret Ave to Dead End

11th 1/2 – Margaret Ave to Dead End

12th St – Margaret Ave to Dead End

13th St – Margaret Ave to Dead End

13th St – Ash St to Barbour Ave

4th Ave – 12th St to 13th St

12th St – 3rd Ave to 4th Ave

7th St – Hulman St to Washington St

8th St – Lafayette to Maple

Spruce St – 8th St to 13th St

Clay – 13th St to 19th St

Dahlen – 13th St to 19th St

Spang – 13th St to 19th St

Berne – 19th St to Lafayette

21st St – Boston to Winslow

23rd St – Spang to Winslow

29th St – Hulman St to Poplar

Washington St – 3rd to 7th (Brick Restore/Partial Reconstruction)

Hulman St – 3rd St to 13th St

29th St Cul-De-Sac – N of Ohio

30th St Cul-De-Sac – N of Ohio

31st St Cul-De-Sac – N of Ohio

32nd St Cul-De-Sac – N of Ohio

Pavement Preservation – Microsurface (City Funded)

13th St – Mulberry St to 5th Ave

13th St – Barbour Ave to Lost Creek Bridge Approach

13th St – Lost Creek Bridge Approach to Ft Harrison

4th Parkway – Indiana to Savanna

Red River – 4th Parkway to 3rd Parkway

Indiana – 4th Parkway to 3rd Parkway

Detroit – 4th Parkway to 3rd Parkway

Savana – 4th Parkway to 3rd Parkwa